A number of items may be part of the schedule data for the project. The amount of additional detail will vary, but the data should include all the following items EXCEPT

A number of items may be part of the schedule data for the project. The amount of additional detail will vary, but the data should include all the following items EXCEPTSchedule data for the project schedule includes a number of items as it collects the information used to describe and control the schedule. It includes schedule milestones, schedule activities, activity attributes, and assumptions and constraints. It may include resource histograms, alternate schedules, contingency reserves cash-flow projections, and order and delivery schedules.

Question:

A number of items may be part of the schedule data for the project. The amount of additional detail will vary, but the data should include all the following items EXCEPT

Options:

Schedule activities

Activity attributes

Identified assumptions

Resource breakdown structure

Correct Answer

The Correct Answer for this Question is

Resource breakdown structure

Leave a Comment