A project manager seeking insight on previous stakeholder management plans and their effectiveness should evaluate:
Question:
A project manager seeking insight on previous stakeholder management plans and their effectiveness should evaluate:
Options:
Historical information and the lessons-learned database.
Historical information and the stakeholder register.
Organizational process assets and the lessons-learned database.
Project documents and historical information.
Correct Answer
The Correct Answer for this Question is
Historical information and the lessons-learned database.