You are the project manager of the HJK project for your organization. You and the project team have created risk responses for many of the risk events in the project. A teaming agreement is an example of what risk response?
Question:
A teaming agreement is an example of what risk response?
Options:
Transference
Acceptance
Mitigation
Sharing
Correct Answer
The Correct Answer for this Question is
Sharing