All the following elements are organizational process asset updates, resulting from closing a project or phase EXCEPT____________All the elements are outputs of the close project or phase processes, but the final product, service, or result transition is not part of the organizational process assets. It is an output on its own and involves the product that the project was created to produce.
Question:
All the following elements are organizational process asset updates, resulting from closing a project or phase EXCEPT____________
Options:
Project files
Project or phase closure documents
Historical information
Final product, service, or result transition
Correct Answer
The Correct Answer for this Question is
Final product, service, or result transition