Assume you are working on a multi-phase project as your project is planned to last three years. A best practice is to_____________

Assume you are working on a multi-phase project as your project is planned to last three years. A best practice is to_____________The business case is an input to the develop project charter process. On a multi-phase project, it should be reviewed periodically to ensure the project is on track to deliver the business benefits.

Question:

Assume you are working on a multi-phase project as your project is planned to last three years. A best practice is to_____________

Options:

Periodically review the business case

Use a single prime contractor and have this contractor award any subcontracts

Rely on your PMO for guidance

Set up a tight matrix’

Correct Answer

The Correct Answer for this Question is

Periodically review the business case