Correct Answer for the Question – Assume you have been working with your sponsor to prepare you charter, and you plan to present it to your Steering Committee on Friday. You are managing a software project, and the business need stated that you should use agile for the first time in our company rather than waterfall. In the Develop Project Charter process, this is then______________ is given below
Assume you have been working with your sponsor to prepare you charter, and you plan to present it to your Steering Committee on Friday. You are managing a software project, and the business need stated that you should use agile for the first time in our company rather than waterfall. In the Develop Project Charter process, this is then______________
Tool and technique
Part of the enterprise environment factors as an input to this process
A high-level requirement
Stated in the strategic plan as a tool and technique in this process
Correct Answer
The Correct Answer for this Question is
A high-level requirement
Explanation
The Question – Assume you have been working with your sponsor to prepare you charter, and you plan to present it to your Steering Committee on Friday. You are managing a software project, and the business need stated that you should use agile for the first time in our company rather than waterfall. In the Develop Project Charter process, this is then______________ has been answered correctly and answers for the question is A high-level requirement
More about these Exams
These Exam Questions and the order of these questions keep changing. but the answers are obviously same. so if you don’t find a question after another we suggest you search it in the search box and we are sure you’ll find it. you can bookmark this site for Quick access in future.
We hope you found it helpful don’t forget to leave a comment if you feel a need to correct or ask we’re always here to help.
you can find more here at Certout
Feel free to contact via comment or email.
Happy Learning
Cheers, Team Certout