Based on quality control measurements on your manufacturing project, management realizes that immediate corrective action is required to the material requirements planning (MRP) system to minimize rework. To implement the necessary changes you should follow_________If the recommended corrective or preventive actions or a defect repair require a change to any of the project management plans, a change request should be prepared in conformance with the perform integrated change control process.
Question:
Based on quality control measurements on your manufacturing project, management realizes that immediate corrective action is required to the material requirements planning (MRP) system to minimize rework. To implement the necessary changes you should follow_________
Options:
The organization’s quality policy
The quality management plan
Established operational definitions and procedures
A defined integrated change control process
Correct Answer
The Correct Answer for this Question is
A defined integrated change control process