Which of the following documents can the sponsor review to determine the project’s performance?

Correct Answer for the Question – Which of the following documents can the sponsor review to determine the project’s performance? is given below Despite receiving regular updates, a sponsor learns a project recently slipped.Which of the following documents can the sponsor review to determine the project’s performance? (Select two.) Status report Communication plan Issue log Project … Read more

When the plan changed to ship the deliverables to a new location. To determine the answer, the project manager should FIRST review the:

Correct Answer for the Question – When the plan changed to ship the deliverables to a new location. To determine the answer, the project manager should FIRST review the: is given below A project sponsor wants to know when the plan changed to ship the deliverables to a new location. To determine the answer, the project … Read more

Which of the following should be notified?

Correct Answer for the Question – Which of the following should be notified? is given below A primary work location is unsafe due to a gas leak. The project manager has implemented the business continuity plan and authorized relocation to an alternate site.Which of the following should be notified? Sponsor PMO Affected team members Project team … Read more

Which of the following documents will the stakeholders MOST likely find information on these events?

Correct Answer for the Question – Which of the following documents will the stakeholders MOST likely find information on these events? is given below A project encountered a problem and reached a milestone. In which of the following documents will the stakeholders MOST likely find information on these events? Issues log Change log Status report Meeting … Read more

Which of the following team members should provide an update?

Correct Answer for the Question – Which of the following team members should provide an update? is given below A project manager needs status on the project timeline.Which of the following team members should provide an update? Product owner Business analyst Scheduler Sponsor Correct Answer The Correct Answer for this Question is Scheduler Explanation The Question … Read more

Which of the following documents should the PM use to obtain a response?

Correct Answer for the Question – Which of the following documents should the PM use to obtain a response? is given below A PM is reviewing bids from vendors and has a question.Which of the following documents should the PM use to obtain a response? Project schedule RFP Quotation RFI Correct Answer The Correct Answer for … Read more

A critical issue has developed in an active project, and the project manager wants to notify the 20-person global project manager use FIRST to relay this information?

Correct Answer for the Question – A critical issue has developed in an active project, and the project manager wants to notify the 20-person global project manager use FIRST to relay this information? is given below A critical issue has developed in an active project, and the project manager wants to notify the 20-person global project … Read more

Which of the following is the BEST risk response strategy?

Correct Answer for the Question – Which of the following is the BEST risk response strategy? is given below A project team is in the process of risk planning. One of the team members identifies a weather-related risk, which may cause delivery delays.Which of the following is the BEST risk response strategy? Exploit Enhance Mitigate Communicate … Read more

A resource is assigned to two projects with two scheduled tasks that complete at the same time.

Correct Answer for the Question – A resource is assigned to two projects with two scheduled tasks that complete at the same time. is given below A resource is assigned to two projects with two scheduled tasks that complete at the same time.This is known as: shared resource contention intraproject resource contention interproject resource contention dedicated … Read more

Which of the following documents ensures two parties do not share contractually binding information?

Correct Answer for the Question – Which of the following documents ensures two parties do not share contractually binding information? is given below Which of the following documents ensures two parties do not share contractually binding information? C&D letter RFI NDA MOU Correct Answer The Correct Answer for this Question is NDA Explanation The Question – … Read more