Which of the following documents can the sponsor review to determine the project’s performance?

Correct Answer for the Question – Which of the following documents can the sponsor review to determine the project’s performance? is given below Despite receiving regular updates, a sponsor learns a project recently slipped.Which of the following documents can the sponsor review to determine the project’s performance? (Select two.) Status report Communication plan Issue log Project … Read more

Which of the following team members should provide an update?

Correct Answer for the Question – Which of the following team members should provide an update? is given below A project manager needs status on the project timeline.Which of the following team members should provide an update? Product owner Business analyst Scheduler Sponsor Correct Answer The Correct Answer for this Question is Scheduler Explanation The Question … Read more

Which of the following documents should the PM use to obtain a response?

Correct Answer for the Question – Which of the following documents should the PM use to obtain a response? is given below A PM is reviewing bids from vendors and has a question.Which of the following documents should the PM use to obtain a response? Project schedule RFP Quotation RFI Correct Answer The Correct Answer for … Read more

A critical issue has developed in an active project, and the project manager wants to notify the 20-person global project manager use FIRST to relay this information?

Correct Answer for the Question – A critical issue has developed in an active project, and the project manager wants to notify the 20-person global project manager use FIRST to relay this information? is given below A critical issue has developed in an active project, and the project manager wants to notify the 20-person global project … Read more

Which of the following is the BEST risk response strategy?

Correct Answer for the Question – Which of the following is the BEST risk response strategy? is given below A project team is in the process of risk planning. One of the team members identifies a weather-related risk, which may cause delivery delays.Which of the following is the BEST risk response strategy? Exploit Enhance Mitigate Communicate … Read more

A resource is assigned to two projects with two scheduled tasks that complete at the same time.

Correct Answer for the Question – A resource is assigned to two projects with two scheduled tasks that complete at the same time. is given below A resource is assigned to two projects with two scheduled tasks that complete at the same time.This is known as: shared resource contention intraproject resource contention interproject resource contention dedicated … Read more

Which of the following documents ensures two parties do not share contractually binding information?

Correct Answer for the Question – Which of the following documents ensures two parties do not share contractually binding information? is given below Which of the following documents ensures two parties do not share contractually binding information? C&D letter RFI NDA MOU Correct Answer The Correct Answer for this Question is NDA Explanation The Question – … Read more

Under an Agile methodology, standup meetings occur:

Correct Answer for the Question – Under an Agile methodology, standup meetings occur: is given below Under an Agile methodology, standup meetings occur: daily twice daily weekly ad hoc Correct Answer The Correct Answer for this Question is daily Explanation The Question – Under an Agile methodology, standup meetings occur: has been answered correctly and answers … Read more

A new contractor joining the project team is an example of:

Correct Answer for the Question – A new contractor joining the project team is an example of: is given below A new contractor joining the project team is an example of: offshoring offboarding rightsizing outsourcing Correct Answer The Correct Answer for this Question is outsourcing Explanation The Question – A new contractor joining the project team … Read more

Which of the following information does the project risk register typically contain?

Correct Answer for the Question – Which of the following information does the project risk register typically contain? is given below Which of the following information does the project risk register typically contain? Type of risk, identified risk, risk response, impact of risk, severity of risk Type of risk, project task, risk response, impact of risk, … Read more