Correct Answer for the Question – During Sprint Planning, the architect is constanly estimating higher than everyone else, and team members are increasing their estimates to accommodate her. is given below
During Sprint Planning, the architect is constanly estimating higher than everyone else, and team members are increasing their estimates to accommodate her.This is an example of:
Dominating
Influencing
Dictating
Anchoring
Correct Answer
The Correct Answer for this Question is
Anchoring
Explanation
The Question – During Sprint Planning, the architect is constanly estimating higher than everyone else, and team members are increasing their estimates to accommodate her. has been answered correctly and answers for the question is Anchoring
More about these Exams
These Exam Questions and the order of these questions keep changing. but the answers are obviously same. so if you don’t find a question after another we suggest you search it in the search box and we are sure you’ll find it. you can bookmark this site for Quick access in future.
We hope you found it helpful don’t forget to leave a comment if you feel a need to correct or ask we’re always here to help.
you can find more here at Certout
Feel free to contact via comment or email.
Happy Learning
Cheers, Team Certout