Question:

How many times should each stage of the Plan, Do, Check, Act (PDCA) cycle be visited?

Options:

Each stage should be carried out once in the order Plan-Do-Check-Act

There should be a single Plan,then the Do-Check-Act cycle should be repeated multiple times to implement Continual Improvement

There should be a single Plan and Do,then Check and Act should be carried out multiple times to implement Continual Improvement

The entire cycle should be repeated multiple times to implement Continual Improvement

Correct Answer

The Correct Answer for this Question is

The entire cycle should be repeated multiple times to implement Continual Improvement