If operations on a work package were estimated to cost $1,500 and finish today but, instead, have cost $1,350 and are only two-thirds complete, the cost variance is_______

If operations on a work package were estimated to cost $1,500 and finish today but, instead, have cost $1,350 and are only two-thirds complete, the cost variance is_______CV is calculated by EV – AC, or $1,500(2/3) – $1,350 = -$350.

Question:

If operations on a work package were estimated to cost $1,500 and finish today but, instead, have cost $1,350 and are only two-thirds complete, the cost variance is_______

Options:

$150

($150)

($350)

($500)

Correct Answer

The Correct Answer for this Question is

($350)