Inputs to the Plan Schedule Management process include:

Correct Answer for the Question – Inputs to the Plan Schedule Management process include: is given below

Inputs to the Plan Schedule Management process include:

Organizational process assets and the project charter,

Enterprise environmental factors and schedule tools.

Time tables and Pareto diagrams.

Activity attributes and resource calendars.

Correct Answer

The Correct Answer for this Question is

Organizational process assets and the project charter,

Explanation

The Question – Inputs to the Plan Schedule Management process include: has been answered correctly and answers for the question is Organizational process assets and the project charter,

More about these Exams

These Exam Questions and the order of these questions keep changing. but the answers are obviously same. so if you don’t find a question after another we suggest you search it in the search box and we are sure you’ll find it. you can bookmark this site for Quick access in future.

We hope you found it helpful don’t forget to leave a comment if you feel a need to correct or ask we’re always here to help.

you can find more here at Certout

Feel free to contact via comment or email.

Happy Learning

Cheers, Team Certout

Leave a Comment