Managing change to the scope baseline is the main objective of the process of control scope. The scope baseline consists of the following components

Managing change to the scope baseline is the main objective of the process of control scope. The scope baseline consists of the following componentsEXCEPT______________The scope management plan is not part of the scope baseline. However, both the scope baseline and the scope management plan are a part of the larger project management plan.

Question:

Managing change to the scope baseline is the main objective of the process of control scope. The scope baseline consists of the following components

Options:

Project scope statement

WBS

WBS dictionary

Scope management plan

Correct Answer

The Correct Answer for this Question is

Scope management plan