Managing change to the scope baseline is the main objective of the process of control scope. The scope baseline consists of the following componentsEXCEPT______________The scope management plan is not part of the scope baseline. However, both the scope baseline and the scope management plan are a part of the larger project management plan.
Question:
Managing change to the scope baseline is the main objective of the process of control scope. The scope baseline consists of the following components
Options:
Project scope statement
WBS
WBS dictionary
Scope management plan
Correct Answer
The Correct Answer for this Question is
Scope management plan