Match the following activities with the Deming Cycle stages1.Monitor, Measure and Review2.Continual Improvement3.Implement Initiatives4.Plan for Improvement
Question:
Match the following activities with the Deming Cycle stages
Options:
1 Plan, 2 Do, 3 Check, 4 Act
3 Plan, 2 Do, 4 Check, 1 Act
4 Plan, 3 Do, 1 Check, 2 Act
2 Plan, 3 Do, 4 Check, 1 Act
Correct Answer
The Correct Answer for this Question is
4 Plan, 3 Do, 1 Check, 2 Act