One way to evaluate the project schedule performance is to______Performance reviews are a tool and technique used in control schedule and includes trend analysis, critical path method, critical chain method, and earned value management. In terms of the critical path method, the emphasis is on comparing progress along the critical path to determine schedule status. Variance on the critical path will have a direct impact on the project’s end date; evaluating progress of activities or near critical paths can identify schedule risk. After the variance is known, the project team can take corrective action to bring performance in line with the plan.
Question:
One way to evaluate the project schedule performance is to______
Options:
Use the project management information system (PMIS)
Determine the percent complete of in-progress schedule activities
Establish a schedule change control system
Determine the total float variance
Correct Answer
The Correct Answer for this Question is
Determine the total float variance