Overlooking negative stakeholders can result in a/an:

Correct Answer for the Question – Overlooking negative stakeholders can result in a/an: is given below

Overlooking negative stakeholders can result in a/an:

decreased likelihood of conflicting interests between stakeholders.

decreased likelihood of the projects progress being impeded

increased likelihood of project failure.

increased likelihood of project success.

Correct Answer

The Correct Answer for this Question is

increased likelihood of project failure.

Explanation

The Question – Overlooking negative stakeholders can result in a/an: has been answered correctly and answers for the question is increased likelihood of project failure.

More about these Exams

These Exam Questions and the order of these questions keep changing. but the answers are obviously same. so if you don’t find a question after another we suggest you search it in the search box and we are sure you’ll find it. you can bookmark this site for Quick access in future.

We hope you found it helpful don’t forget to leave a comment if you feel a need to correct or ask we’re always here to help.

you can find more here at Certout

Feel free to contact via comment or email.

Happy Learning

Cheers, Team Certout

Leave a Comment