Which tool or technique is NOT used for schedule control?
Which tool or technique is NOT used for schedule control?Work performance data is an input to control schedule. Question: Which tool or technique is NOT used for schedule control? Options: Performance reviews Project management software Work performance information Leads and lags Correct Answer The Correct Answer for this Question is Work performance information