The business needs, assumptions, and constraints and the understanding of the customers needs and high-level requirements are documented in the:

The business needs, assumptions, and constraints and the understanding of the customers needs and high-level requirements are documented in the:

Question:

The business needs, assumptions, and constraints and the understanding of the customers needs and high-level requirements are documented in the:

Options:

Project management plan.

Project charter.

Work breakdown structure.

Stakeholder register.

Correct Answer

The Correct Answer for this Question is

Project charter.