Correct Answer for the Question – The process of establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule is known as: is given below
The process of establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule is known as:
Plan Schedule Management.
Develop Project Charter.
Develop Schedule.
Plan Scope Management.
Correct Answer
The Correct Answer for this Question is
Plan Schedule Management.
Explanation
The Question – The process of establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule is known as: has been answered correctly and answers for the question is Plan Schedule Management.
More about these Exams
These Exam Questions and the order of these questions keep changing. but the answers are obviously same. so if you don’t find a question after another we suggest you search it in the search box and we are sure you’ll find it. you can bookmark this site for Quick access in future.
We hope you found it helpful don’t forget to leave a comment if you feel a need to correct or ask we’re always here to help.
you can find more here at mnccertified
Feel free to contact via comment or email.
Happy Learning
Cheers, Team MNCcertified