The zero duration of milestones in project planning occurs because milestones:

Correct Answer for the Question – The zero duration of milestones in project planning occurs because milestones: is given below

The zero duration of milestones in project planning occurs because milestones:

Are unpredictable and challenge the Plan Schedule Management process.

Occur at random times in the project plans.

Represent a moment in time such as a significant project point or event.

Represent both significant and insignificant points in the project and are difficult to anticipate.

Correct Answer

The Correct Answer for this Question is

Represent a moment in time such as a significant project point or event.

Explanation

The Question – The zero duration of milestones in project planning occurs because milestones: has been answered correctly and answers for the question is Represent a moment in time such as a significant project point or event.

More about these Exams

These Exam Questions and the order of these questions keep changing. but the answers are obviously same. so if you don’t find a question after another we suggest you search it in the search box and we are sure you’ll find it. you can bookmark this site for Quick access in future.

We hope you found it helpful don’t forget to leave a comment if you feel a need to correct or ask we’re always here to help.

you can find more here at Certout

Feel free to contact via comment or email.

Happy Learning

Cheers, Team Certout

Leave a Comment