Validate scope works hand-in-hand with control quality and generally follows control quality. A tool and technique used in validate scope that is not used in control quality isBoth processes use inspection. Validate scope also uses group-decision making techniques to reach a conclusion when the validation is performed by the project team and other stakeholders. Methods to reach a group decision include: unanimity, majority, plurality, and dictatorship.
Question:
Validate scope works hand-in-hand with control quality and generally follows control quality. A tool and technique used in validate scope that is not used in control quality is
Options:
Group decision-making techniques
Inspection
Statistical sampling
Variance analysis
Correct Answer
The Correct Answer for this Question is
Group decision-making techniques