The project charter has just been signed off. There were items in the charter that described market conditions which could affect the project and also resource limitations on the project.These are examples of what?
Question:
What?
Options:
Assumptions
Constraints
Economic consumption
Authority level of the Project Manager
Correct Answer
The Correct Answer for this Question is
Constraints