What is reviewed and updated to provide the information needed by the Project Board for assessing the continuing viability of the project?

During the Managing a Stage Boundary process, what is reviewed and updated to provide the information needed by the Project Board for assessing the continuing viability of the project?

Question:

What is reviewed and updated to provide the information needed by the Project Board for assessing the continuing viability of the project?

Options:

Benefits Review Plan

Product Status Account

Business Case

Project Plan

Correct Answer

The Correct Answer for this Question is

Business Case