What is the MOST appropriate approach to managing this situation?

While implementing an approved change, a critical defect was introduced. Removing the defect will delay the product delivery. What is the MOST appropriate approach to managing this situation?

Question:

What is the MOST appropriate approach to managing this situation?

Options:

Utilize the change control process.

Crash the schedule to fix the defect.

Leave the defect in and work around it.

Fast-track the remaining development.

Correct Answer

The Correct Answer for this Question is

Utilize the change control process.