You are the project manager of the NNH Project. In this project you have created a contingency response that the schedule performance index should be less than 0.93. The NHH Project has a budget at completion of $945,000 and is 45 percent complete though the project should be 49 percent complete. The project has spent $455,897 to reach the 45 percent complete milestone. What is the project’s schedule performance index?
Question:
What is the project’s schedule performance index?
Options:
($37,800)
0.93
0.92
1.06
Correct Answer
The Correct Answer for this Question is
0.92