Correct Answer for the Question – What should be used to calculate the forecast? is given below
As part of a mid-project evaluation, the project sponsor has asked for a forecast of the total project cost. What should be used to calculate the forecast?
BAC
EAC
ETC
WBS
Correct Answer
The Correct Answer for this Question is
EAC
Explanation
The Question – What should be used to calculate the forecast? has been answered correctly and answers for the question is EAC