You are the project manager of the AFD project for your company. You are working with the project team to reassess existing risk events and to identify risk events that have not happened and whose relevancy to the project has passed. What should you do with these events that have not happened and would not happen now in the project?
Question:
What should you do with these events that have not happened and would not happen now in the project?
Options:
Add the risks to the risk register
Add the risks to a low-prioritywatchlist
Close the outdated risks
Add the risk to the issues log
Correct Answer
The Correct Answer for this Question is
Close the outdated risks