You are the project manager for BlueWell Inc. Your current project is a high priority and high profile project within your organization. You want to identify the project stakeholders that will have the most power in relation to their interest on your project. This will help you plan for project risks, stakeholder management, and ongoing communication with the key stakeholders in your project. In this process of stakeholder analysis, what type of a grid or model should you create based on these conditions?
Question:
What type of a grid or model should you create based on these conditions?
Options:
Stakeholder power/interest grid
Influence/impact grid
Salience model
Stakeholder register
Correct Answer
The Correct Answer for this Question is
Stakeholder power/interest grid