When a project review should be conducted, you believe it is important to review performance at the conclusion of each phase. The objective of such a review is to________

Although your company’s project life cycle does not mandate when a project review should be conducted, you believe it is important to review performance at the conclusion of each phase. The objective of such a review is to________The review at the end of a project phase is called a phase-end review. The purpose of this review is to determine whether the project should continue to the next phase for detecting and correcting errors while they are still manageable and for ensuring that the project remains focused on the business need it was undertaken to address.

Question:

When a project review should be conducted, you believe it is important to review performance at the conclusion of each phase. The objective of such a review is to________

Options:

Determine how many resources are required to complete the project according to the project baseline

Adjust the schedule and cost baselines based on past performance

Obtain customer acceptance of project deliverables

Determine whether the project should continue to the next phase

Correct Answer

The Correct Answer for this Question is

Determine whether the project should continue to the next phase