When an activity cannot be estimated with a reasonable degree of confidence, the work within the activity is decomposed into more detail using which type of estimating?
Question:
When an activity cannot be estimated with a reasonable degree of confidence, the work within the activity is decomposed into more detail using which type of estimating?
Options:
Bottom-up
Parametric
Analogous
Three-point
Correct Answer
The Correct Answer for this Question is
Bottom-up