Correct Answer for the Question – When an Agile project team receives an “emergency request” during an iteration, which is the best first step that the Agile project manager should take? is given below
When an Agile project team receives an “emergency request” during an iteration, which is the best first step that the Agile project manager should take?
Stop work on unfinished user stories and work on the urgent request.
Call a team meeting and change the iteration scope to include the request.
Provide the customer with options provided by the project team.
Explain that the team cannot do the added work until the next iteration.
Correct Answer
The Correct Answer for this Question is
Provide the customer with options provided by the project team.
Explanation
The Question – When an Agile project team receives an “emergency request” during an iteration, which is the best first step that the Agile project manager should take? has been answered correctly and answers for the question is Provide the customer with options provided by the project team.
More about these Exams
These Exam Questions and the order of these questions keep changing. but the answers are obviously same. so if you don’t find a question after another we suggest you search it in the search box and we are sure you’ll find it. you can bookmark this site for Quick access in future.
We hope you found it helpful don’t forget to leave a comment if you feel a need to correct or ask we’re always here to help.
you can find more here at mnccertified
Feel free to contact via comment or email.
Happy Learning
Cheers, Team MNCcertified