When are tolerances for a Work Package agreed?

When are tolerances for a Work Package agreed?

Question:

When are tolerances for a Work Package agreed?

Options:

When accepting a Work Package

As work on each product within the Work Package begins

Once ail products have been developed and approved

When the Stage Plan is authorized by the Project Board

Correct Answer

The Correct Answer for this Question is

When accepting a Work Package