When should the Project Board refer to corporate or programme management for a decision?
Question:
When should the Project Board refer to corporate or programme management for a decision?
Options:
The stage requires resources
It is forecast that project level tolerance will be exceeded
The Senior Supplier or Senior User needs to be changed
Any request for change needs to be approved
Correct Answer
The Correct Answer for this Question is
It is forecast that project level tolerance will be exceeded