When should the Project Board refer to corporate or programme management for a decision?

When should the Project Board refer to corporate or programme management for a decision?

Question:

When should the Project Board refer to corporate or programme management for a decision?

Options:

The stage requires resources

It is forecast that project level tolerance will be exceeded

The Senior Supplier or Senior User needs to be changed

Any request for change needs to be approved

Correct Answer

The Correct Answer for this Question is

It is forecast that project level tolerance will be exceeded