The only output of the perform qualitative risk analysis are risk register updates. When the project manager updates the risk register he will need to include several pieces of information including all of the following except for which one?
Question:
When the project manager updates the risk register he will need to include several pieces of information including all of the following except for which one?
Options:
Trends in qualitative risk analysis
Risk probability-impact matrix
Watchlist of low-priority risks
Risks grouped by categories
Correct Answer
The Correct Answer for this Question is
Risk probability-impact matrix