The best approach to estimate the work on a project when using story points is to have:

Team members assign estimates by averaging Planning Poker cards.

The most senior team member prepare the estimates.

Two or three senior team members estimate and take the average of their times.

The team work together to agree on estimates in a group setting.

Correct Answer

The Correct Answer for this Question is

The team work together to agree on estimates in a group setting.

Explanation

The Question – When using story points is to have: has been answered correctly and answers for the question is The team work together to agree on estimates in a group setting.

More about these Exams

These Exam Questions and the order of these questions keep changing. but the answers are obviously same. so if you don’t find a question after another we suggest you search it in the search box and we are sure you’ll find it. you can bookmark this site for Quick access in future.

We hope you found it helpful don’t forget to leave a comment if you feel a need to correct or ask we’re always here to help.

you can find more here at Certout

Feel free to contact via comment or email.

Happy Learning

Cheers, Team Certout

Leave a Comment