You work as a project manager for BlueWell Inc. There has been a delay in your project work that is adversely affecting the project schedule. You decided, with your stakeholders’ approval, to fast track the project work to get the project done faster. When you fast track the project which of the following are likely to increase?
Question:
When you fast track the project which of the following are likely to increase?
Options:
Costs
Quality control concerns
Human resource needs
Risks
Correct Answer
The Correct Answer for this Question is
Risks