You are the project manager of the GHG project for your company. You have identified the project risks, completed qualitative and quantitative analysis, and created risk responses. You also need to document how and when risk audits will be performed in the project. Where will you define the frequency of risk audits?
Question:
Where will you define the frequency of risk audits?
Options:
Risk response plan
Quality management plan
Risk management plan
Schedule management plan
Correct Answer
The Correct Answer for this Question is
Risk management plan