Which baselines make up the performance measurement baseline?
Question:
Which baselines make up the performance measurement baseline?
Options:
Scope baseline, cost baseline, and schedule baseline
Scope baseline, project management baseline, and quality baseline
Cost baseline, schedule baseline, and risk baseline
Cost baseline, project management baseline, and schedule baseline
Correct Answer
The Correct Answer for this Question is
Scope baseline, cost baseline, and schedule baseline