Correct Answer for the Question – Which Collect Requirements output links the product requirements to the deliverables that satisfy them? is given below
Which Collect Requirements output links the product requirements to the deliverables that satisfy them?
Requirements documentation
Requirements traceability matrix
Project management plan updates
Project documents updates
Correct Answer
The Correct Answer for this Question is
Requirements traceability matrix
Explanation
The Question – Which Collect Requirements output links the product requirements to the deliverables that satisfy them? has been answered correctly and answers for the question is Requirements traceability matrix
More about these Exams
These Exam Questions and the order of these questions keep changing. but the answers are obviously same. so if you don’t find a question after another we suggest you search it in the search box and we are sure you’ll find it. you can bookmark this site for Quick access in future.
We hope you found it helpful don’t forget to leave a comment if you feel a need to correct or ask we’re always here to help.
you can find more here at Certout
Feel free to contact via comment or email.
Happy Learning
Cheers, Team Certout