Which describes risk impact?
Question:
Which describes risk impact?
Options:
Timeframe within which the risk might occur
The trigger that occurred giving rise to the risk
The effect of the risk on the delivery of project objectives
How likely the risk is to occur in a given project situation
Correct Answer
The Correct Answer for this Question is
The effect of the risk on the delivery of project objectives