Which describes risk probability?

Which describes risk probability?

Question:

Which describes risk probability?

Options:

Level of risks which the project can tolerate before escalating to the Project Board

Probable effect on the project delivering its objectives

Timeframe within which the risk may occur

A measure of the likelihood of the risk occurring

Correct Answer

The Correct Answer for this Question is

A measure of the likelihood of the risk occurring