Which describes risk probability?
Question:
Which describes risk probability?
Options:
Level of risks which the project can tolerate before escalating to the Project Board
Probable effect on the project delivering its objectives
Timeframe within which the risk may occur
A measure of the likelihood of the risk occurring
Correct Answer
The Correct Answer for this Question is
A measure of the likelihood of the risk occurring