If the Project Board instructs the Project Manager to implement a request for change, which document would contain details of that change?
Question:
Which document would contain details of that change?
Options:
Checkpoint Report
Highlight Report
Issue Report
Product Status Account
Correct Answer
The Correct Answer for this Question is
Issue Report