Which document would contain details of that change?

If the Project Board instructs the Project Manager to implement a request for change, which document would contain details of that change?

Question:

Which document would contain details of that change?

Options:

Checkpoint Report

Highlight Report

Issue Report

Product Status Account

Correct Answer

The Correct Answer for this Question is

Issue Report