Assume you are managing a project to implement an electronic medical record system in your ophthalmologist’s office. You have been working to identify your stakeholders to then make sure everyone is committed to it as some people have been working in this office for more than 20 years and are comfortable with the manual approach. At this point, you have documented assessment information, which includes______________The stakeholder register contains assessment information as a key component. The assessment information includes: major requirements, main expectations, potential influence in the project, and the phase in the project life cycle with the most interest.

Question:

Which includes______________

Options:

Role in the project

Whether the stakeholder is a supporter, is neutral, or is resistant

Potential influence in the project

Organization position

Correct Answer

The Correct Answer for this Question is

Potential influence in the project