Which input is exclusive to the Determine Budget process?

In Project Cost Management, which input is exclusive to the Determine Budget process?

Question:

Which input is exclusive to the Determine Budget process?

Options:

Scope baseline

Organizational process assets

Project schedule

Resource calendars

Correct Answer

The Correct Answer for this Question is

Resource calendars