In Project Cost Management, which input is exclusive to the Determine Budget process?
Question:
Which input is exclusive to the Determine Budget process?
Options:
Scope baseline
Organizational process assets
Project schedule
Resource calendars
Correct Answer
The Correct Answer for this Question is
Resource calendars