Which is a PRINCE2 time-driven control?

Which is a PRINCE2 time-driven control?

Question:

Which is a PRINCE2 time-driven control?

Options:

End Stage Report

Project Brief

Project Initiation Documentation

Checkpoint Report

Correct Answer

The Correct Answer for this Question is

Checkpoint Report