Which is a PRINCE2 time-driven control?
Question:
Which is a PRINCE2 time-driven control?
Options:
End Stage Report
Project Brief
Project Initiation Documentation
Checkpoint Report
Correct Answer
The Correct Answer for this Question is
Checkpoint Report