Which is NOT a requirement of a Stage Plan?

Which is NOT a requirement of a Stage Plan?

Question:

Which is NOT a requirement of a Stage Plan?

Options:

Produced to an appropriate level of detail to enable day-to-day control

Produced near to the end of the previous management stage

Approved and signed-off by Project Assurance

Approved at the end of a management stage

Correct Answer

The Correct Answer for this Question is

Approved and signed-off by Project Assurance