Question:

Which Knowledge Areas include processes from the Closing Process Group?

Options:

Project Quality Management and Project Time Management

Project Scope Management and Project Risk Management

Project Stakeholder Management and Project Cost Management

Project Integration Management and Project Procurement Management

Correct Answer

The Correct Answer for this Question is

Project Integration Management and Project Procurement Management