On the electric company project the government implemented a regulatory change associated with the electricity sub-station upgrade project that required the company to spend an additional $400,000 US on the project. This type of cost and activity best relates to which of the following?
Question:
Which of the following?
Options:
Known unknowns
Unknown unknowns
Management reserve
Risk management
Correct Answer
The Correct Answer for this Question is
Unknown unknowns