Which of the following correctly lists the configuration management activities included in the Integrated Change Control process?

Correct Answer for the Question – Which of the following correctly lists the configuration management activities included in the Integrated Change Control process? is given below

Which of the following correctly lists the configuration management activities included in the Integrated Change Control process?Configuration control is focused on the specification of both the deliverables and the processes; while change control is focused on identifying, documenting, and approving or rejecting changes to the project documents, deliverables, or baselines.Some of the configuration management activities included in the Perform Integrated Change Control process are as follows:Configuration identification. Identification and selection of a configuration item to provide the basis for which the product configuration is defined and verified, products and documents are labeled, changes are managed, and accountability is maintained.Configuration status accounting. Information is recorded and reported as to when appropriate data about the configuration item should be provided. This information includes a listing of approved configuration identification, status of proposed changes to the configuration, and the implementation status of approved changes.Configuration verification and audit. Configuration verification and configuration audits ensure the composition of a project’s configuration items is correct and that corresponding changes are registered, assessed, approved, tracked, and correctly implemented. This ensures the functional requirements defined in the configuration documentation have been met.

Configuration definition, configuration status accounting, configuration monitoring and control

Configuration identification, configuration status accounting, configuration verification and audit

Configuration identification, configuration status reporting, configuration verification and audit

Configuration definition, configuration status reporting, configuration monitoring and Control

Correct Answer

The Correct Answer for this Question is

Configuration identification, configuration status accounting, configuration verification and audit

Explanation

The Question – Which of the following correctly lists the configuration management activities included in the Integrated Change Control process? has been answered correctly and answers for the question is Configuration identification, configuration status accounting, configuration verification and audit

More about these Exams

These Exam Questions and the order of these questions keep changing. but the answers are obviously same. so if you don’t find a question after another we suggest you search it in the search box and we are sure you’ll find it. you can bookmark this site for Quick access in future.

We hope you found it helpful don’t forget to leave a comment if you feel a need to correct or ask we’re always here to help.

you can find more here at Certout

Feel free to contact via comment or email.

Happy Learning

Cheers, Team Certout

Leave a Comment