Which of the following includes how requirements activities will be planned, tracked, and reported?

Correct Answer for the Question – Which of the following includes how requirements activities will be planned, tracked, and reported? is given below

Which of the following includes how requirements activities will be planned, tracked, and reported?

Configuration management plan

Scope baseline

Requirements management plan

Schedule baseline

Correct Answer

The Correct Answer for this Question is

Requirements management plan

Explanation

The Question – Which of the following includes how requirements activities will be planned, tracked, and reported? has been answered correctly and answers for the question is Requirements management plan

More about these Exams

These Exam Questions and the order of these questions keep changing. but the answers are obviously same. so if you don’t find a question after another we suggest you search it in the search box and we are sure you’ll find it. you can bookmark this site for Quick access in future.

We hope you found it helpful don’t forget to leave a comment if you feel a need to correct or ask we’re always here to help.

you can find more here at Certout

Feel free to contact via comment or email.

Happy Learning

Cheers, Team Certout

Leave a Comment